Client: Berkeley Group c/o Mainstay
Clients Agent: LBB Chartered Surveyors
Duration: Phase 1 – 16 weeks
Phase 2 – 12 weeks
Value: £410,000
Details:
- 30 units, 3 communal/landlord areas, 1,400 m2
- Lift up and remove existing rotten timber decking and support structure
- Apply Proteus cold lay overcoating system to existing roof deck
- Supply and fit balcony slabs on a pedestal supports
Key Objectives/Challenges:
- Access was restricted to one point for each phase causing a lot of material movement by the workforce around this extensive building
- Major supply problems with the stone slabs due to Covid 19